2026-DOC 00003 Published On: 05/11/2026
Question: Can you clarify / help us reconcile, 1. this statement from Appendix O: “ii. A Facility that bids both solar-only and SPWS resource types must have the same maximum export at the Point of Interconnection for both resource types.”, with, 2. this statement in Section C.(b); “storage resources must be… sized 35-40% of the maximum export MWac of the Facility’s POI”. Can you provide examples of what solar + storage configurations would work within this framework?
Answer: For the 2026 Solar and Solar Paired with Storage RFP:
2026-DOC 00002 Published On: 05/04/2026
Question: Will there be a general interconnection guidance document released just like in 2025? Trying to ascertain the amount for the IC Study Fee and IC Study Deposit.
Answer: Yes, it will be posted by May 15, 2026.
2026-DOC 00001 Published On: 03/24/2026
Question: Where is the heatmap located?
Answer: The heatmap will be available in mid-April 2026. It will be shared on OATI OASIS (www.oasis.oati.com) for Duke Energy Progress and Duke Energy Carolinas.